Second Test of DARC Dirt 1- April 13, 2008
A Draft Report
  This report patched together from two Blog Postings
  FURNACE CONSTRUCTION
I had mentioned that I made a clandestine trip to my local dump specifically to 
get a half barrel sized metal drum. As luck would have it - I found exactly the 
size I was looking for. The idea was to build a more durable version of the dependable 
'Econo Norse' firebrick smelter. 
(Go HERE to see the layout 
drawing) 
 
The drum was just about exactly the same size as a hexagon arrangement of standard 
hard bricks - stacked the normal three sets tall. The result is a smelter containment 
that is roughly 20 cm internal diameter, but still at the normal plus 40 cm above 
the tuyere.
 
I cut the required holes and ports into the barrel, and welded in some external 
and internal fittings and supports. On the lower view, you can see the removeable 
'hatch' that covers over two of the lower ring of bricks which can be pried loose 
for either a large tap arch or for a possible bottom extraction. Although these 
bricks are also backed up with the clay and charcoal fines cobb, they were wrapped 
with paper first to make removal later easier.The section of barrel that was cut 
away to create the hatch is held back in place by a length of flat bar which also 
forms a simple handle.
  
A 
rectangular hole was cut the same size as the brick that holds the tuyere and 
sits above it. This brick is made of low density fire brick which has been cut 
in half to about 2 cm thick. If past experience proves correct, this material 
should radiate excess heat on its outside surface - and reduce erosion.
  
Looking 
down from the top, the cobb packing holding the bricks into place can be seen. 
The packing is a rough triangle in the gabs of hexagon pattern of the bricks. 
An air space has been deliberately left between the flat sides of the bricks and 
the curvature of the circular barrel. The hope is that this will allow some of 
the excess heat to bleed off into the gaps. 
  
 
Hopefully the smelter will prove to be reusable. The reduced size and the hard 
  support provided by the barrel should make the furnace body easy to move on 
  a two wheeled cart. Although the fire bricks make it fairly heavy, two people 
  should be able to pick it up to load it into a vehicle. 
SMELT DAY
The weather the day before had turned cold again, with forecast of snow on smelt day. For that reason (expecting the worst and feeling weak) I set up the smelter inside on the main floor of the workshop. (For those who have never been to the Wareham Forge, the building is a converted circa 1930's drive shed. The main walls are poured concrete, with a pole construction roof above. The distance from the dirt floor to the peak is twenty feet. )
This smelt was to be a second test of the DARC 
Dirt 1 - bog iron ore analog developed by Gus GIssing. The first 
test (at Smeltfest 08) was not ideal, as the smelter layout was a new type 
we had little experience with. The dynamics of the 'bellows plate' type furnace, 
and its taller stack height combined to a low yield and very high carbon bloom. 
In this case the mix of 80% 'Spanish Red' (Fe2O3) / 10% silica sand / 10% flour 
had been air drying for about a week. The cold and wet weather had slowed this 
process. At the time of the smelt the ore material was dry enough to easily handle, 
but still slightly damp to the touch. It was broken up from the large plate pieces 
(roughly 1 cm thick) by tapping through a 2.5 cm wire grid with a wooden mallet. 
A second screen, about 3 mm, was used to separate out the fine dust. (This step 
was not done for the Smeltfest test). The result was pulling off about 20 % of 
the prepared material as dust. As the analog was not baked this time, this dust 
can easily be incorporated into the next batch by just adding water. It was generally 
thought that the pieces from the 2.5 cm grid may have been a bit too large. Use 
of a 1.5 cm grid is likely ideal. 
  
The team consisted of: Ken Cook - smelt master Darrell Markewitz - assisting (and 
coaching) Neil Peterson - measuring and recording Lloyd Johnson came up to observe 
and assist with the final hammering of the bloom. There was considerably less 
prep work required, other than the construction of the more durable metal can 
for the smelter. The charcoal used was the Black 
Diamond from Bruce Cowan, which was pre-crushed to the ideal size.
This experiment employed a number of new pieces of equipment: 1) The smelter itself, 
which was a smaller variation on our well proven fire brick construction Econo 
Norse furnace. This furnace was 20 cm in diameter, a change which is a considerable 
reduction to our normal size of closer to 30 cm. There was some concern that this 
roughly 40 % reduction in volume might prove a problem with the dynamics of the 
furnace. I was encouraged by Skip Williams' recent experiments with very small 
table top sized furnaces. 
2) The use of the new, larger volume, electric blower I had just purchased. This 
is the same blower used by Sauder & Williams (to great success).
  
It also would be the first time for the new sliding gate air 
  control made up specifically for use with this unit. This would be coupled with 
  the in-line set up for the air speed gauge and pressure gauge.
 
  The extraction was from the bottom of the furnace, which had been constructed 
  with a proportionally large tab arch. The image above shows Ken taking out the 
  two bricks that blocked the arch during the smelt. (This was the first time 
  Ken undertook an extraction.) As it turned out, there was a reasonably large 
  slag block formed. The bloom proved properly positioned, and contained within 
  the correct pool of liquid slag. With a bit of hammering, it was possible to 
  break away the side of the slag and grab out the bloom. 
  The finished bloom is shown above. After a bit of compression hammering, it 
  was decided to slice off a third as seen to give to Lloyd. The bloom was both 
  smaller and less dense than I had hoped for: Bloom Weight - 2 kg Total Ore - 
  18 kg * Total Charcoal - 150 L (about 30 kg) Total Time - 4 1/2 hours (not including 
  pre-heat) The yield is a bit better than it looks at first glance. We baked 
  dry a measured sample of the ore analog, and it was found to contain 12 % water. 
  This puts the 'real' weight of ore used at closer to 15.8 kg. This gives us 
  a yield of about 13%. Still lower than our usual, but enough that the DARC Dirt 
  1 analog is worthy of further testing. There is still a very large mass of hardened 
  slag to break free of the interior of the furnace. This may prove to have other 
  smaller masses of metal contained in it. Certainly it would appear that there 
  is a larger proportion of slag formed than has been seen in past uses of the 
  larger brick furnaces with other ore types. 
      
  Text and photography © 2008, 
  Darrell Markewitz